EVALUATION SCHEDULE

DATE ACTIVITY

9/1

Functional area representatives from both DOE and Ames develop PBCM's for ensuing year

11/1

Proposed PBCMs submitted to Ames Group Manager and Laboratory Director.

12/1

Final PBMMs and relative weights are established.

12/31

December 31 -- Performance period ends.

1/1

Performance Period begins.

2/16

February -- Contractor submits self assessment report to DOE Group Manager.

3/1

DOE conducts its business review to validate the contractor reported levels of performance attained against established objectives and measures and the contractor's assessed overall level of performance in all functional areas through its self-assessment.

4/1

DOE develops draft report and transmits to the Contractor.

4/16

Contractor submits comments on draft report.

5/1

DOE transmits final report to the Contractor.

7/1

Contractor submits mid-year status report to DOE.

NOTE:

The above represents the estimated schedule for the continuing cycle of establishing and evaluating performance under this contract. DOE and the Contractor will review this schedule to determine whether the time frames for each activity should be adjusted in subsequent