Current Issues The licensee has delayed the estimated completion date of
decommissioning activities from late 2001 until late 2002. The delay
is caused by the discovery that contamination had spread behind the
concrete shielding that lines parts of the containment vessel. The
licensee is in the process of removing all of the concrete from the
containment to ensure that contamination is addressed. Because of the
high water table at the site, the area around the containment was
de-watered and the containment was anchored to bedrock to prevent the
containment from becoming buoyant as weight is removed. The NRC staff
continues to evaluate the LTP. |
|